Contract Accounting





A contract is a big job requiring considerable length of time to complete and comprising activities to be done outside the factory promises, viz. construction of a dam or school building, laying down railway lines, etc. Special financial and cost accounting is required to maintain the records of construction contracts. Since each contract involves considerable resources both in terms of men and materials, it is necessary to devise an appropriate accounting system to ascertain the cost and profit made on each contract separately.
Profit on incomplete contracts: At the end of an accounting period it may be found that certain contract have been completed while others are still in process and will be completed in the coming years. The total profits made on completed contract say be safely taken to the credit of the profit and loss account. But the same cannot be done in case of incomplete contracts. These contracts are still in process, and there are possibilities of profits being turned into to losses on account of heavy rise in prices of materials and labor and losses on account of other unforeseen contingencies. At the same time it does not also seem desire able to consider the profits only on completed contracts and ignore completely incomplete ones because this may result in heavy fluctuations in the figure of profit from year to year. A year in which a large number of contracts have been completed will show an abnormal high figure for profit while reserve may be the case in the year in which a large number of contracts remain incomplete. Therefore, profits on incomplete contracts should be considered, of course, after providing adequate sums for meeting unknown contingencies.
There are no hard and fast rules for the calculation of the figures for profit to be taken to the credit of profit and loss account. However, the following rules may be followed:
(a) Profit should be considered in respect of work certified only, work uncertified should always be valued at cost.
(b) No profit should be taken into consideration if the amount of work certified is less than 1/4 of the contract price because in such cases it is not possible to foresee the future clearly.
(c) If the amount of work certified is 1/4 or more but less than1/2 of the contract price, 1/3 of the profit disclosed, as reduced but the percentage of cash received from the contractee, should be taken to the profit and loss account. The balance should be allowed to remain as a reserve.
(d) If the amount of work certified is very much near completion, if possible the total cost of completing the contract should be estimated The estimated total profit on the contract then can be calculated by deducting the total estimated cost from the contract price. The profit and loss should be credited with that proportion of total estimated profit on cash basis, which the work certified bears to the total contract price.
(f) The whole of loss, if any, should be transferred to the profit and loss account.
Cost Plus Contracts: In certain contracts the contractee agrees to pay to the contractor the cost price (usually prime cost) of the work done on the contract plus an agreed percentage thereof by way of overhead expenses and profit. Such contracts are known as cost-plus contracts. The system of cost plus contract costing is employed in cases where it is very difficult for the contractor to quote the contract price because there has been no precedent which he may take as basis. It is also employed where the work to be done is not fixed at the time of placing order for the contract. The method is generally used where government happens to be the contractee. The method suffers from the following disadvantages:
There is no incentive to the contractor to eliminate waste and economies the cost of completing the contract. On the other hand, he is tempted to increase the cost because greater the cost, the greater will be his share of profit. In case of this system the amount of overheads recovered and profit made depends upon the value of materials used, which is subject to considerable price fluctuations. The agreed fixed percentage may, therefore, prove to be either too excessive or too low for covering overheads and profit.
Escalation Clause: Escalation clause is usually provided in the contract as a safeguard against any likely changes in the prices of utilization of material and labor. The clause provides that in case prices of items of raw materials, labor, etc. specified in the contract, change during the execution of the contract, beyond a specified limit over the price prevailing at the time of signing the agreement, the contract price will be suitably adjusted. The term of the contract specify the procedure for calculating such adjustment in order to avoid all future disputes. Thus, such a clause safeguards the interests of both the contractor and contractee in case of fluctuations in the price of materials and labor, etc.
Work in Progress: At the end of the accounting period a contract may still be in progress. The term work in progress refers to the work done so for in respect of the contract, which is still incomplete. It consists of the following:
(1) Working Certified: It refers to the work approved by the contractee. In case of contracts it is the useful practice for the contractor to get the work approved from time to time from the contractee. This is helpful to the contractor in two ways; first in case the contractee finds the work not up to specifications, he may ask the contractor to take corrective actions in time. Second, in contract accounts it is useful practice to have a system of progress payments, i.e., the contractee agrees to pay a certain percentage of the work certified (say, 80 or 90 percent). This is advantageous to the contractor since he gets immediate liquid funds.
(2) Work Uncertified: It refers to the work which has been done by the contractor but not so far approved by the contractee.
Work certified generally includes some profit element also while work uncertified is always valued at cost to the contractor.
Sub Contracts: The contractor may entrust some portion of the work to be done under the contract to a sub-contractor. Usually work of a specialized nature, i.e., steel work, special flooring, etc., is done by sub-contractors, who are responsible to the main contractor. The cost of such sub-contracts is a direct charge against the contract for which the work has been done.

About Author Rashid Javed :

Rashid Javed is an Asian author. He writes articles about various topics of
financial accounting and
managerial accounting such as

six sigma
and
current ratio.


Article Source: http://www.bharatbhasha.net
Article Url: http://www.bharatbhasha.net/finance-and-business.php/222976


Article Added on Wednesday, March 10, 2010
Other Articles by Rashid Javed

Factory Ledger
It is often practical for a manufacturing concern to include a factory ledger in its accounting system. Generally, this procedure is followed when manufacturing operations are far-flung from the main office, or when the nature of such operations requires a large number of accounts. Some accounts relating to manufacturing are kept in factory office books while other are kept in general office books. What accounts and other records be kept in the factory journal and ledger and what accounts and...

Need and Importance of International Accounting Standards IAS
Financial reporting frameworks were initially developed within each country, resulting in significant differences of reporting standards across national boundaries. This caused reporting problems for multinational companies and difficulties for stock market analysts, international investors and economic agencies such as the World Bank and International Monetary Fund. As this information is used to support global investment decisions and to account to international providers of funds, national...

The Role of Accounting in Business Organizations
Accounting information is used in all economic activities, form a kindergarten or a social club, through complex business organizations to national and international authorities. Accountants 'keep the score' of business events, by recording, analyzing and reporting the results for two main reasons: 1. To support (and improve) future decisions - particularly by management 2. To discharge accountability to the providers of the funds used - either higher levels of management or, externally, to...

managerial Skills Articals
A manager's job is varied and complex. Managers need certain skills to perform the duties and activities associated with being a manager. What type of skills does a manager need? Research by Robert L. Katz found that managers needed three essential skills. These are technical skills, human skills and conceptual skills. Technical skills include knowledge of and proficiency in a certain specialized field, such as engineering, computers, cost accounting and management accounting, or manufacturing....

Financial Statement Analysis
All financial statements are essentially historically historical documents. They tell what has happened during a particular period of time. However most users of financial statements are concerned about what will happen in the future. Stockholders are concerned with future earnings and dividends. Creditors are concerned with the company's future ability to repay its debts. Managers are concerned with the company's ability to finance future expansion. Despite the fact that financial statements...

Variable Direct Costing
Variable costing is very important element of cost and management accounting. Variable costing charges products with only those manufacturing costs that vary directly with volume. Only prime costs (direct materials and direct labor) plus variable factory overhead expenses are assigned to inventories, both work in process and finished goods, and to the cost of goods sold. Thus, these variable costs are charged to the product while fixed manufacturing costs are totally expensed in the current...

Factory Overhead Departmentalization
Departmentalization of factory overhead means dividing the plant into parts or sections called departments or cost centers to which expenses are charged. From the accounting point of view, the division of plant into separate segment according to some logical form provides more accurate results and better control. More accurate costing of jobs and products is possible because each department will be charged with overhead rates which are reasonable for that department. A job or product going...

Financial System of More and Less Devolped Countries
In more developed nations, monetary and financial policy plays a major direct and indirect role in governmental efforts designed to expand economic activity in times of unemployment and surplus capacity and to contract that activity in times of excess demand and inflation. Basically, monetary policy works on two principal economic variables: the aggregate supply of money in circulation and the level of interest rates. Expressed in traditional terms, the money supply (currency plus commercial...

Financial and Cost Statements
An indispensable part of any system of accounting is programmed of periodical statements and reports to inform management of the current financial position of the business and of the progress made by, and the costs incurred for, each process, department and division. The number of statements and reports and their characters differ according to the requirements of management of each business enterprise. The following statements and supporting cost reports are commonly prepared for the...

Why Study Managemaet
You may be wondering why you need to study management. If you are an accounting major, a marketing major, or an major other than management, you may not understand how studying management may help you in your career. We can explain the value of studying management by looking at the universality of the management, the reality of work, and the rewards and challenges of being a manager. The Universality of Management: Just how universal is the need of management in organizations? We can say...

Publishers / Webmasters
Tell A Friend
Leave A Comment!
Download this article in PDF
Report Article!
Search through all the articles:


101 Users Online !
Related Articles:
Latest Articles:
 
Business And Finance >> Top 50 Articles on Business And Finance
Category - >
Advertising Advice Affiliate Programs Automobiles
Be Your Own Mentor Careers Communication Consumers
CopyWriting Crime Domain Names DoT com Entrepreneur Corner
Ebooks Ecommerce Education Email
Entertainment Environment Family Finance And Business
Food & Drink Gardening Health & Fitness Hobbies
Home Business Home Improvement Humour House Holds
Internet And Computers Kiddos and Teens Legal Matters Mail Order
Management Marketing Marriage MetaPhysical
Motivational MultiMedia Multi Level Marketing NewsLetters
Pets Psychology Religion Parenting
Politics Sales Science Search Engine Optimization
Site Promotion Sports Technology Travel
Web Development Web Hosting WeightLoss Women's Corner
Writing Miscellaneous Articles Real Estate Arts And Crafts
Aging


Disclaimer: The information presented and opinions expressed in the articles are those of the authors
and do not necessarily represent the views of bharatbhasha.net and/or its owners.


Copyright © AwareINDIA. All rights reserved || Privacy Policy || Terms Of Use || Author Guidelines || Free Articles
FAQs Link To Us || Submit An Article || Free Downloads|| Contact Us || Site Map  || Advertise with Us ||
Click here for Special webhosting packages for visitors of this website only!
Vastu Shastra

Linux Hosting Provided By AwareIndia